Manual › Lean PlanDo Project
LPD Project
Masterplan
- What is a Masterplan? Learn what the Masterplan is, how Lean PlanDo shows it and what you can change in it.
- Masterplan screen Switch between the Masterplan views, zoom the timeline, show only critical works and choose which columns to show.
- Activity features in the Masterplan Open an activity's detailed view or mini widget in the Masterplan, and see what each one shows.
- Export the Masterplan Export the complete Masterplan for Microsoft Project or Primavera, and see which values can differ after import.
- Objectives of the pre-configuration phase Learn why you review the Masterplan before the first Lookahead, and how date changes affect base dates before and after it.
- Edit an activity in pre-configuration Change an activity's name, start date, duration and progress in the pre-configuration phase, from the edit form or by dragging its bar.
- Rename an activity Change the name of a Masterplan activity at any time from its edit form.
- Edit activity dates Advance or delay an activity's dates in the pre-configuration phase, and learn how this sets its base dates.
- Remaining Early Start of an activity Set the date the remaining work of an activity can resume, and learn when you must set it.
- Edit activity duration Change an activity's duration in pre-configuration to set its base duration, and learn what float means.
- Enter work completed (progress) Record work done on an activity before the Masterplan was uploaded, in the pre-configuration phase.
- Add an activity in the Masterplan Add a sub activity under an existing activity in the Masterplan, and learn how parent activities and dependencies affect it.
- Edit an activity in the Masterplan Change an activity's name, dates, base dates or duration after the Lookahead is generated, and learn how delays and progress are recorded.
- Delete an activity Delete an activity from the Masterplan when it is no longer part of the plan. Deleting cannot be undone.
- Add a milestone in the Masterplan Add a milestone to the Masterplan as a sub activity with a duration of 0, then set its date.
- Delete a milestone Delete a milestone from the three-dots menu in the Masterplan, or from its widget in the Masterplan or Lookahead Gantt chart.
- Add an activity dependency Link activities in the Masterplan as predecessors and successors, choose the dependency type and set a lag.
- Edit an activity dependency Edit, disable, enable or delete an activity dependency, and see how each change can move the project end date.
- Delay or advance an activity Move an activity earlier or later in the Masterplan to match progress on site, whether it has started or not.
- Constraints overview Learn what constraints are, the two constraint types, how their status shows in the Gantt chart, and how steps and ETA work.
- Add an activity constraint Add a constraint to an activity, set its type, ETA, assignee and steps, so you can track preparation work before the activity starts.
- Activity constraint ETA Understand a constraint's ETA and change it, to set how many working days before the work starts the constraint must be cleared.
- Manage an activity constraint Open a constraint's detail view, mini widget or timeline view to edit it, check its status and track its steps.
- Update an activity constraint due date Delay or advance an activity constraint by changing the due date of its last step, and see where the delay is recorded.
- Manage steps in an activity constraint Edit the assignee, due date and status of each step in an activity constraint, and read the delay icons.
- Add one constraint to multiple activities or tasks Apply a single constraint to several activities or tasks when one piece of preparation work holds them all up.
- Delete a constraint Delete a constraint from an activity or a task, in the Masterplan or the Lookahead Gantt chart.
- Project critical path See which activities are on the critical path, read their float, and filter the Masterplan to show only critical works.
- Critical milestones Mark a milestone as critical to track its own critical path, colour its flag, and follow its delays in Insights.
- Versions Import a new master schedule from Microsoft Project or Primavera P6 and merge it into your active Masterplan as a new version.
Lookahead
- Generate the Lookahead Generate your project's first 6 or 8 week Lookahead once the Masterplan is pre-configured, and see what the Lookahead screen shows.
- First Lookahead generation See how Lean PlanDo reschedules started and unstarted activities when you generate the first Lookahead, and how it records the delay.
- Task features in the Lookahead Open a task's detailed view or mini widget in the Lookahead, and see what each tab and menu item does.
- Change the Lookahead day Change the weekly Lookahead day in Project Settings, and see how the interim week moves your project to the new day.
- Create a single task Create one task under an activity in the Lookahead, and set its name, dates, sequence number, company and supervisor.
- Create multiple tasks Split one activity into several tasks at once in the Lookahead, with optional links between them.
- Add a task prefix Turn on task prefixes for an activity so every task name shows where it belongs, such as its zone and building level.
- Add a quantity to a task Quantify a task as a physical count, such as 3 columns, so you can update its progress in units instead of percentages.
- Edit a task Change a task's name, description, dates, duration or sequence number, and see how the change affects its activity.
- Delay or advance a task Move a task earlier or later to match site progress, and record the delay reason when the task has base dates.
- Delete a task Remove a task you no longer need from the schedule, and see which tasks cannot be deleted.
- Add a task dependency Link two tasks in the Lookahead so a successor task follows its predecessor, within one activity or across activities.
- Edit a task dependency Change the type or lag of a task dependency, disable it or delete it, so the Lookahead matches the planned construction sequence.
- Cyclic dependency behaviour Learn why Lean PlanDo shows an error when a dependency would make an activity or task both successor and predecessor.
- Add a task constraint Add a constraint to a task in the Lookahead, set its steps and due dates, and read its colour and status.
- Task constraint ETA Learn what a task constraint's ETA means and how to edit it in the Lookahead.
- Manage a task constraint Edit, reassign or delete a task constraint in the Lookahead, and read the delay icons.
- Update a task constraint due date Delay or advance a task constraint by changing the due date of its last step.
- Manage steps under a task constraint Edit the status, due date and assignee of each step in a task constraint.
- Commit a task to the Do tab Commit a constraint-free task in the Lookahead so it appears in the Do tab for the Do week.
- Uncommit a task from the Do tab Uncommit a task in the Do week when its work cannot go ahead, from the Lookahead, the detailed view or the Dashboard.
- Workable backlog Read the Should Do, Can Do, Will Do and Did counters in the Lookahead and Do tab headers.
- Save an activity as a template Save an activity's tasks and constraints as a template so you can reuse them on similar activities in the Lookahead.
- Apply a template Apply a saved template to an activity in the Lookahead to create its tasks and constraints automatically.
- Export two weeks of Lookahead tasks Export the first two weeks of your Lookahead, with tasks, as an Excel file.
Do List
- Do tab Understand the Do tab: the committed weekly work plan, with its constraints, workflows and tasks for the Do week.
- Update task progress Record daily progress on committed tasks in the Do tab, using the progress widget or the detailed view.
- Reset task progress Correct wrong progress on a task by undoing the last entry or resetting all progress.
- Update a task constraint from the Do tab Change the status, due date or assignee of a constraint's steps from the Do tab.
- Confirm and lock the Do week Confirm the week's progress and constraint updates in the Do tab, and see what must be done before you can.
- Review past weeks in the Do tab Look back at the tasks and constraints done and confirmed in past weeks, using the week selector in the Do tab.
- How progress is calculated Learn how Lean PlanDo calculates planned, actual and expected progress for leaf and summary activities.
Insights
- Lean PlanDo Insights See what Lean PlanDo Insights shows about your project's performance and how to open it.
- Project status Read the Project Status widget to see if your project is on time and when it is expected to finish.
- Project progress Read the Weekly Project Progress (Time) S-curve to compare planned, actual and expected progress.
- Commitment and reliability Understand the four weekly indicators of commitment and reliability, and how each one is calculated.
- Workable backlogs Read the Weekly Workable Backlog graph: Should Do, Can Do, Will Do and Did tasks for each Do week.
- Plan reliability Read the plan reliability pie charts to see how many activities started, lasted and finished as planned.
- Critical project delays See which critical path activities and constraints delayed the project, by how many days, and why.
- Delay classification See the delay reasons in Lean PlanDo, how Insights groups them, and how to read the Delay Classification chart and table.
- Delay responsibility Read the Delay Responsibility charts in Insights to see which parties caused the most delays.
- Work delays Find every recorded delay on the Insights Weekly tab, and change a delay's reason or responsible party.
- Activities performance analysis Use four Insights charts to find the most delayed, extended, shortened and early finished activities in your project.