Enter work completed (progress)

Record work done on an activity before the Masterplan was uploaded, in the pre-configuration phase.

In the pre-configuration phase, you can record the work on an activity that was done before you uploaded the Masterplan to Lean PlanDo.

  1. Find out the percentage (%) of work completed for the activity.
  2. Open the activity's edit form (see Edit an activity in pre-configuration) and enter it in Total Progress. The Expected Start field is now labelled Actual Start, and the Rem. Early Start and Rem. Duration fields appear.
  3. Set Actual Start, the date the work on the activity actually started.
  4. Set Rem. Early Start (the date the remaining work of a started activity or task resumes). See Remaining Early Start of an activity.