Lean PlanDo manual › Do List
Do tab
Understand the Do tab: the committed weekly work plan, with its constraints, workflows and tasks for the Do week.
The Do tab is your project's committed weekly work plan. It holds the tasks that the main contractor and sub contractors have committed to work on in the Do week. The Do week is the first week of the Lookahead, where tasks can be committed; it should be the current calendar week.
It also holds each constraint (work that must be cleared before a task can be done, such as getting site access) to update in the Do week. The Do tab shows constraints that fall in the Do week, and constraints whose steps fall in it. A step is one part of a constraint; a step not done shows as an empty circle with a grey outline, a done step as a filled green circle.
If committed work cannot start in the Do week for any reason, you must uncommit it from the Do tab and delay it to the right date.
Views
The Do tab has these views:
- Constraints: all constraints in the Do week, steps in the Do week, and steps that passed the Lookahead (the 6-week or 8-week plan where activities are broken down into smaller tasks) with a Not Done status.
- Workflows (Flow projects only): the workflows with steps pending in the Do week, one tab per discipline.
- Tasks: all tasks committed to the Do week. Tick List view to see the tasks as a list instead of bars.
To update a task's progress, read Update task progress.
Last updated 2019-09-25. Part of Do List in the Lean PlanDo manual. Lean PlanDo by Lean Station.