Activities performance analysis

Use four Insights charts to find the most delayed, extended, shortened and early finished activities in your project.

Under activities performance, you can analyse the top activities behind your project's delays in four charts. Open Insights from the project menu. The four charts are on the Overview tab:

  • Top Delayed Activities
  • Top Extended Activities
  • Top Shortened Activities
  • Top Early Finished Activities

In every chart, click an activity name to open its detail window and see more about its delays.

Activities Performance Analysis (Overview)

Chart 1: Top Delayed Activities

Chart 1 shows the most delayed activities. In a sample project, 2nd storey slab is the most delayed. Its actual start was 186 days later than its base start date (base dates are the dates an activity has when the first Lookahead is generated).

When you click an activity, its detail window opens.

Chart 2: Top Extended Activities

Chart 2 shows the activities whose duration grew the most. In a sample project, Ground slab soil treatment/lean concrete grew the most: its actual duration was 146 days against a base duration of 9 days.

Chart 3: Top Shortened Activities

Chart 3 shows the activities whose duration shrank the most. In a sample project, Blk 3+4-B1 (archi works) was 40 days shorter than its base duration.

Chart 4: Top Early Finished Activities

Chart 4 shows the activities that finished earliest. In a sample project, Cast pile-caps - DT2 finished 325 days before its base end date.

Last updated 2020-03-31. Part of Insights in the Lean PlanDo manual. Lean PlanDo by Lean Station.