Work delays
Find every recorded delay on the Insights Weekly tab, and change a delay's reason or responsible party.
The Work Delays widget lists every delay recorded in your project. Use it to see what was delayed, by how much and why.
Find the widget
- Open Insights.
- Click the Weekly tab.
- Choose This Week, Last Week or Past Weeks.
For each delay, the widget shows:
- the activity name
- the number of days delayed
- who delayed it
- when it was delayed
- the reason for the delay
- the company responsible for the delay
Change a delay reason or comment on a delay
Users from the Client company can change the reason and the responsible party for a delay. They can also comment on it. Insights saves every change as history, so you can see it at any time.
-
Click the activity or task name. A pop-up opens with options to edit and comment on the delay.
-
Under Edit delay:, select another reason or responsible party from the drop-down lists.
-
Click Save to keep the change.
-
To comment, open the Comments tab. You also see other users' comments on this delay.
-
Type your comment in Enter comments here.
-
Click Comment.