Lean PlanDo manual › Lookahead
Task constraint ETA
Learn what a task constraint's ETA means and how to edit it in the Lookahead.
ETA is the number of working days between a constraint's last step and the start of the task. The last step must be due at least that many working days before the start.
- If ETA = 5, the constraint must be cleared at least 5 working days before the task's start date.
- The ETA is set in days, from 0 to 100. The default is 1.
- You can edit the ETA at any time until the constraint is done.
- Changing the ETA never affects the task's start date. It can affect the due dates of the constraint and its steps.
- The minimum ETA is 0. This means the task can start on the same day the constraint is done.
Edit the ETA
- Double-click the constraint (the circle in line with its task).
- Click the Pencil (Edit) button.
- Change the value in the ETA box.
- Click the tick button to save.
For ETA on activity constraints, see Activity constraint ETA.